Director's Claim Board History
Updated 03/26/2008
Meeting Date |
Meeting Type |
Project |
Claim Type |
Demand |
Award |
|||
|
Amount (Dollars) |
Time (Days) |
Amount (Dollars) |
Time (Days) |
||||
10/10/95 |
Hearing |
931019 |
Plan Ambiguity |
$148,920 |
0 |
$121,995 |
0 |
|
12/05/95 |
Hearing |
940848 |
Plan Ambiguity |
$13,283 |
0 |
$13,283 |
0 |
|
01/30/96 |
Hearing |
940645 |
Denied use of Haul Road |
$410,000 |
0 |
$0 |
0 |
|
03/28/96 |
Hearing |
950501 |
Plan Ambiguity |
$93,100 |
0 |
$55,524 |
0 |
|
04/05/96 |
Document |
950587 |
Plan Ambiguity, Delay |
$7,875 |
0 |
$5,513 |
0 |
|
06/12/96 |
Hearing |
950384 |
Plan Ambiguity, Delay, Disputed Final Quantities, Home Office Overhead, Inefficiency |
$9,359 |
5 |
$8,100 |
5 |
|
06/12/96 |
Hearing |
930906 |
Plan Ambiguity, Delay |
$137,759 |
0 |
$17,582 |
0 |
|
10/01/96 |
Hearing |
931030 |
Delay Costs |
$120,583 |
0 |
$0 |
0 |
|
10/01/96 |
Document |
950454 |
Plan Ambiguity |
$7,650 |
0 |
$0 |
0 |
|
10/18/96 |
Hearing |
950595 |
Plan Ambiguity |
$24,887 |
0 |
$24,887 |
0 |
|
10/18/96 |
Document |
954005 |
Non Performance |
$11,897 |
0 |
$0 |
0 |
|
10/25/96 |
Hearing |
930758 |
Delay, Home Office Overhead, Forced Acceleration, Inefficiency |
$542,015 |
0 |
$19,318 |
0 |
|
11/18/96 |
Hearing |
960147 |
Plan Ambiguity |
$196,516 |
0 |
$0 |
0 |
|
01/10/97 |
Document |
950339 |
Equipment Compensation on Force Account |
$15,066 |
0 |
$3,013 |
0 |
|
01/10/97 |
Hearing |
930796 |
Negligent Inspection |
$47,103 |
0 |
$15,600 |
0 |
|
03/03/97 |
Hearing |
950526 |
Sole Source Delay |
$0 |
46 |
$0 |
0 |
|
03/03/97 |
Document |
960395 |
Misleading Plan Note |
$5,305 |
0 |
$4,627 |
0 |
|
05/19/97 |
Document |
960168 |
Improper Instructions from Inspector |
$6,471 |
0 |
$6,474 |
0 |
|
05/19/97 |
Document |
950561 |
Plan Ambiguity |
$6,468 |
0 |
$0 |
0 |
|
05/19/97 |
Document |
960300 |
Subsurface Changed Conditions |
$8,535 |
0 |
$1,425 |
0 |
|
05/19/97 |
Document |
960313 |
Dewatering |
$5,660 |
0 |
$0 |
0 |
|
06/20/97 |
Hearing |
950384 |
Delay |
$68,743 |
27 |
$8,221 |
13 |
|
06/26/97 |
Hearing |
960059 |
Plan Ambiguity, Forced Acceleration |
$104,049 |
0 |
$14,194 |
0 |
|
08/13/97 |
Hearing |
960423 |
Plan Ambiguity |
$74,731 |
0 |
$20,733 |
0 |
|
08/13/97 |
Hearing |
960422 |
Plan Ambiguity |
$17,080 |
0 |
$8,743 |
0 |
|
02/03/98 |
Hearing |
960216 |
Culvert excavation and backfill plan ambiguity |
$16,745 |
0 |
$3,670 |
0 |
|
02/03/98 |
Document |
940436 |
Plan Ambiguity |
$19,846 |
0 |
$19,846 |
0 |
|
03/23/98 |
Document |
980302 |
Piling change |
$6,305 |
14 |
$0 |
0 |
|
03/23/98 |
Hearing |
960670 |
Pile driving |
$12,426 |
0 |
$0 |
0 |
|
03/23/98 |
Hearing |
960752 |
Delay |
$27,031 |
0 |
$20,630 |
0 |
|
05/01/98 |
Hearing |
970219 |
Change in warranty asphalt placement |
$21,278 |
0 |
$0 |
0 |
|
07/28/98 |
Hearing |
950659 |
Dewatering - unusual amount of groundwater |
$18,488 |
11 |
$3,999 |
11 |
|
07/31/98 |
Hearing |
970483 |
Pile Driving |
$44,687 |
0 |
$13,554 |
0 |
|
08/04/98 |
Hearing |
950413 |
Delay Costs |
$16,041 |
0 |
$7,858 |
0 |
|
09/24/98 |
Hearing |
970240 |
Embankment Failure Correction |
$127,911 |
0 |
$0 |
0 |
|
11/03/98 |
Hearing |
960760 |
A+B Incentive wording |
$104,000 |
0 |
$104,000 |
0 |
|
11/03/98 |
Hearing |
970091 |
A+B Incentive wording |
$90,000 |
75 |
$66,000 |
32 |
|
10/30/98 |
Document |
960492 |
Plan Ambiguity |
$27,500 |
0 |
$25,723 |
0 |
|
10/30/98 |
Hearing |
960703 |
Utility Delay |
$5,644 |
85 |
$739 |
55 |
|
01/29/99 |
Hearing |
970166 |
Subsurface conditions, Constructability, Home Office Overhead |
$450,064 |
0 |
$319,292 |
0 |
|
05/27/99 |
Hearing |
950573 |
Compensation for Extra Work |
$41,668 |
0 |
$17,636 |
0 | |
08/05/99 |
Hearing |
960305 |
Home Office Overhead for disruption of cash flow |
$48,991 |
0 |
$0 |
55 |
|
09/21/00 |
Hearing |
970139 |
Plan ambiguity |
$111, 415 |
0 |
$0 |
0 |
|
Total: |
$3,273,096 |
263 |
$952,179 |
116 |
Portion of Demand Awarded: |
Compensation: |
29 % |
Time: |
44 % |
Claims Decided by Board: |
Hearing: |
31 |
Documents: |
12 |
|
Pending: |
3 |