Director's Claim Board History

Updated 03/26/2008

Meeting Date

Meeting Type

Project

Claim Type

Demand

Award

 

     

Amount

(Dollars)

Time

(Days)

Amount

(Dollars)

Time

(Days)

10/10/95

Hearing

931019

Plan Ambiguity

$148,920

0

$121,995

0

12/05/95

Hearing

940848

Plan Ambiguity

$13,283

0

$13,283

0

01/30/96

Hearing

940645

Denied use of Haul Road

$410,000

0

$0

0

03/28/96

Hearing

950501

Plan Ambiguity

$93,100

0

$55,524

0

04/05/96

Document 

950587

Plan Ambiguity, Delay

$7,875

0

$5,513

0

06/12/96

Hearing

950384

Plan Ambiguity, Delay, Disputed Final Quantities, Home Office Overhead, Inefficiency

$9,359

5

$8,100

5

06/12/96

Hearing

930906

Plan Ambiguity, Delay

$137,759

0

$17,582

0

10/01/96

Hearing

931030

Delay Costs

$120,583

0

$0

0

10/01/96

Document 

950454

Plan Ambiguity

$7,650

0

$0

0

10/18/96

Hearing

950595

Plan Ambiguity

$24,887

0

$24,887

0

10/18/96

Document 

954005

Non Performance

$11,897

0

$0

0

10/25/96

Hearing

930758

Delay, Home Office Overhead, Forced Acceleration, Inefficiency

$542,015

0

$19,318

0

11/18/96

Hearing

960147

Plan Ambiguity

$196,516

0

$0

0

01/10/97

Document 

950339

Equipment Compensation on Force Account

$15,066

0

$3,013

0

01/10/97

Hearing

930796

Negligent Inspection

$47,103

0

$15,600

0

03/03/97

Hearing

950526

Sole Source Delay

$0

46

$0

0

03/03/97

Document

960395

Misleading Plan Note

$5,305

0

$4,627

0

05/19/97

Document

960168

Improper Instructions from Inspector

$6,471

0

$6,474

0

05/19/97

Document

950561

Plan Ambiguity

$6,468

0

$0

0

05/19/97

Document

960300

Subsurface Changed Conditions

$8,535

0

$1,425

0

05/19/97

Document

960313

Dewatering

$5,660

0

$0

0

06/20/97

Hearing

950384

Delay

$68,743

27

$8,221

13

06/26/97

Hearing

960059

Plan Ambiguity, Forced Acceleration

$104,049

0

$14,194

0

08/13/97

Hearing

960423

Plan Ambiguity

$74,731

0

$20,733

0

08/13/97

Hearing

960422

Plan Ambiguity

$17,080

0

$8,743

0

02/03/98

Hearing

960216

Culvert excavation and backfill plan ambiguity

$16,745

0

$3,670

0

02/03/98

Document

940436

Plan Ambiguity

$19,846

0

$19,846

0

03/23/98

Document 

980302

Piling change

$6,305

14

$0

0

03/23/98

Hearing

960670

Pile driving

$12,426

0

$0

0

03/23/98

Hearing

960752

Delay

$27,031

0

$20,630

0

05/01/98

Hearing

970219

Change in warranty asphalt placement

$21,278

0

$0

0

07/28/98

Hearing

950659

Dewatering - unusual amount of groundwater

$18,488

11 

$3,999

11

07/31/98

Hearing

970483

Pile Driving

$44,687

0

$13,554

0

08/04/98

Hearing

950413

Delay Costs

$16,041

0

$7,858

0

09/24/98

Hearing

970240

Embankment Failure Correction

$127,911

0

$0

0

11/03/98

Hearing

960760

A+B Incentive wording

$104,000

0

$104,000

0

11/03/98

Hearing

970091

A+B Incentive wording

$90,000

75

$66,000

32

10/30/98

Document 

960492

Plan Ambiguity

$27,500

0

$25,723

0

10/30/98

Hearing

960703

Utility Delay

$5,644

85

$739

55

01/29/99

Hearing

970166

Subsurface conditions, Constructability, Home Office Overhead

$450,064

0

$319,292

0

05/27/99

Hearing

950573

Compensation for Extra Work

$41,668

0

$17,636

0

08/05/99

Hearing

960305

Home Office Overhead for disruption of cash flow

$48,991

0

$0

55

09/21/00

Hearing

970139

Plan ambiguity

$111, 415

0

$0

0

     

Total:

$3,273,096

263

$952,179

116

 

Portion of Demand Awarded:

Compensation:

29 %

Time:

44 %

 

Claims Decided by Board:

Hearing:

31

Documents:

12

Pending:

3